Week 7 Case study 8.

Our papers are 100% unique and written following academic standards and provided requirements. Get perfect grades by consistently using our writing services. Place your order and get a quality paper today. Rely on us and be on schedule! With our help, you'll never have to worry about deadlines again. Take advantage of our current 20% discount by using the coupon code GET20


Order a Similar Paper Order a Different Paper


Week 7 Case study 8.3 P.308-310 Pinto


Boston’s Central Artery/Tunnel Project

Since the “Big Dig” project was first introduced in the previous edition of this textbook, a number of additional events have occurred that make it important for us to revisit the original story and update the current status of this monumental project. When it was opened in 1959, Boston’s Central Artery highway was hailed as a marvel of engineering and forwardthinking urban planning. Designed as an elevated six-lane highway through the middle of the city, the highway was intended to carry a traffic volume of 75,000 vehicles a day. Unfortunately, by the early 1980s, the Central Artery was burdened by a daily volume of more than 200,000 vehicles, a nearly threefold increase over the anticipated maximum traffic levels. The result was some of the worst urban congestion in the country, with traffic locked bumper to bumper for more than 10 hours each day. At over four times the national average, the accident rate for the Central Artery added to commuters’ misery. Clearly, the Central Artery— a crumbling, overused, and increasingly dangerous stretch of highway— had outlived its usefulness. Michael Dwyer/Alamy Figure 8.10 Boston’s Big Dig The solution to the problem was the advent of the Central Artery/Tunnel (CA/T) project, commonly known to people from the Boston area as the “Big Dig.” Under the supervision of the Massachusetts Turnpike Authority and using federal and state funding, the CA/T project comprises two main elements: (1) replacing the aging elevated roadway with an 8- to 10-lane underground expressway directly beneath the existing road, with a 14-lane, two-bridge crossing of the Charles River, and (2) extending Interstate 90 through a tunnel beneath South Boston and the harbor to Logan Airport. Originally conceived and initiated in the early 1980s, the project was a continuous activity (some would say “headache”) in the city for more than 20 years. The technical challenges in the Big Dig were enormous. Employing at its peak about 5,000 workers, the project included the construction of eight miles of highway, 161 lane miles in all, almost half below ground. It required the excavation of 16 million cubic yards of soil, enough to fill the New England Patriots’ football stadium 16 times, and used 3.8 million cubic yards of concrete. The second major challenge was to perform these activities without disrupting existing traffic patterns or having a deleterious effect on the current highway system and its traffic flows. Thus, while miles of tunnels were being excavated underneath the old Central Artery, traffic volume could not be slowed on the elevated highway.

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now

The project had been a source of controversy for several years, most notably due to its soaring costs and constantly revised budget. At the time of the project’s kickoff in 1983, the original projections for the project’s scope assumed a completion date of 1998 and onetime funding from the federal government to cover 60% of the project’s original $2.5 billion budget. In fact, the budget and schedule have been revised upward nearly constantly since the project kicked off. Consider the following budget levels: year 1983 1989 1992 1996 2000 2003 Budget (in billions) 2.56 4.44 6.44 10.84 14.08 14.63 Final cost projections soared to over $14.5 billion and the project officially wrapped up in late 2004, or seven years late. Cost estimates and subsequent expenditures were so bad that by 2000, a federal audit of the project concluded that the Big Dig was officially bankrupt. One component of the federal audit concluded that a major cause for runaway project costs was due to poor project management oversight. Specifically, it was found that project management routinely failed to hold contractors to their bids or to penalize them for mistakes, resulting in huge cost increases for the Big Dig. Because of the intense public scrutiny and sensitive nature of the project, managers also stopped tracking or publicly acknowledging escalating costs, fearing that the political backlash could cripple the project. In fact, Taxpayers for Common Sense, a nonpartisan watchdog group, charged that the project’s economics became so bad that managers delayed budgeting for contracts worth $260 million to a consulting firm because they could not offset such a large cost in the short term. In response to public outcry over the delays and rising costs, the project manager submitted his resignation. Not surprisingly, the citizens of Boston have viewed the opening of the Big Dig with a genuine sense of ambivalence. Though a technological marvel that will undoubtedly improve the lives of its users, while reducing carbon monoxide emissions and improving the “green” reputation of the city, the project proved to be such a financial morass that public officials quietly canceled a planned celebration of a major section’s opening. Finger pointing and a search for the causes of the Big Dig’s poor cost estimation and control were vigorous. For its part, the Massachusetts Turnpike Authority planned a $150 million lawsuit against the firms that managed the project, arguing that many of the cost overruns could be attributed to poor project management and oversight. Increasingly, the question being asked was: Were original cost estimates for the CA/T given in good faith or were they “tuned” to meet political realities? That is, did officials deliberately underestimate true project costs, fearing that the project would not have been approved in the beginning if the public was aware of its likely cost and scope? If so, the result has been to leave a sour taste in the mouths of the taxpaying public, convinced that the CA/T project represents a combination of brilliant technical achievement coupled with poor estimation and lax control. Former Massachusetts House Speaker Thomas Finnerman put the matter directly: “You’d be much, much better off saying upfront, factually, ‘Hey, it’s going to take umpteen years likely and umpteen billions dollars,’ rather than selling it as a kind of smoke and mirrors thing about, ‘Oh, it’s two billion and a couple of years’ work.'” aftermath: Reconsidering the Big Dig Since the completion of the Big Dig, you would expect the commotion to have died down, the complaints to have been resolved, and the people of Boston to have become used to the advantages of this enormous project. Unfortunately, that has not been the case. Since its “completion” in early 2004, bad press, disasters, and accountability continue to dog the Central Tunnel/ Artery system. In 2001, prior to the completion of the project, thousands of leaks began appearing in the ceiling of sections of the tunnel system. The cause? Records suggest that the primary contractor for the concrete pouring, Modern Continental, failed to remove debris prior to pouring concrete, resulting in flaws, cavities, and pockets of weakness in the ceiling and walls of the tunnels. In May 2006, six employees of the main supplier of concrete were arrested for falsifying records. In fact, 2006 was a very bad year for the Big Dig for a variety of reasons. On July 10, 2006, the bolt and epoxy system holding four sections (12 tons) of concrete ceiling panels failed, causing a section to collapse onto the tunnel roadway and kill a passenger in a car passing beneath the section at the time. That month, a detailed inspection of the ceiling panels throughout the tunnel system identified an additional 242 bolts that were already showing signs of stress! The tunnel system was shut down for the month of August for inspection and repairs. Also in August, the state assumed control of the Central Tunnel/Artery from the Turnpike Authority, citing the TA’s poor record of supervision and effective project control. The tragedy became something close a to farce when the Turnpike Authority and Federal Highway Administration refused to release critical documents to the state, including: • Deficiency reports flagging initial substandard work • Construction change orders and contract revisions • Inspection reports on workmanship and building material quality Until the court system orders the release of all project documents, we may never know the extent of mismanagement and poor decision making that dogged the development of the CT/A. From a public relations perspective, however, the fighting between state and federal authorities over oversight and control of the troubled project is a continuing black eye for all parties involved. In early 2008, the contractors for the Big Dig, including primary contractors Bechtel and Parson Brinckerhoff, were ordered to pay $450 million to settle the state’s lawsuit over the 2006 tunnel collapse. Though this settlement does not absolve the contractors from future lawsuits, it does settle some of the more egregious failures that occurred while they led the project. Michael Sullivan, the U.S. Attorney who led the lawsuit, noted that the contractors originally made a profit of about $150 million from the Big Dig; however, “They lost money as a result of the failures that occurred under their watch.”


Questions

Writerbay.net

Hi, student! You are probably looking for a free essay here, right? The most obvious decision is to order an essay from one of our writers. It won’t be free, but we have an affordable pricing policy. In such a manner, you can get a well-written essay on any topic. Let us cover any of your writing needs!


Order a Similar Paper Order a Different Paper